FACTS AND RULES OF THUMB
1. Compressed air is
the most inefficient utility in the plant
to get 1 hp work from an air motor requires approximately 30 scfm inlet air at 90 psig
which requires 6-7 hp at the compressor shaft to produce this compressed air
assuming a 90% efficient motor, this translates into 7-8 hp of electrical power to deliver 1 hp of compressed air to the plant floor
Net efficiency is >12.5% of the input energy is available for useful work energy
But, on average half of the air is wasted
2. Operating costs reductions are worth more than sales and productivity dollars
Cost reduction vs. productivity / profitability
$100,000 in costs reduction = $2,000,000 sales at 5% net profit
Turning off 100 bhp of air compressor power @ $0.08 / kwh =
$56,000 year in operating costs at 8760 hrs = $1,120,000 sales
Savings potential in systems average
35% to 50% in smaller systems <300 bhp
20% to 30% in larger systems >1000 bhp
3. RULE OF THUMB Compressed air costs
Total Compressed Air Costs @ $0.06 /kWh
A 100 scfm application costs $1.22 per hour to support or $10,655 per year at 8760 hrs
Or, $0.20 per 1000 scf
1 HP air motor costs - $3,516 per year (8760 hrs)
1 HP electric motor - $426 per year
Energy savings on the demand side of the system are at a factor of > 8X -10 X if electric vs. air powered
4. Estimate energy
costs by :
Compressors - ratio of actual amps to nameplate amps times the motor nameplate HP and convert to kW
or nameplate HP X .746 / .92 = kW
Refrig Dryers nameplate amps X 460v X .85 X 1.732 / 1000 = kW
or refrig dryer capacity / 200 cfm = kW
Cycling refrig dryers offer significant energy savings
Heated desiccant dryers capacity / 60 cfm = kW
Dewpoint based purge control offers significant energy savings
Cooling systems nameplate amps of pump motors and fans and convert to Kw
Or 3% of total compressor kW for cooling energy
Total kW x hours x $0.08 /kWh = total energy costs
Total energy costs / .70 = total operating costs $$$
(these calculations assume full load on each compressor but still provides an estimate of costs)
5. Annual Electricity Cost (measurement formula)
full load amps) x (voltage) x (1.732) x pf x hours x rate
1,000
Where:
full load amps =
average of three phases
voltage =
line to line voltage
pf =
power factor
hours =
annual hours of operation
rate =
electricity cost in $/kWh
The full load amps and voltage are the measured values
Get power factor (pf) from motor manufacturer (use .85 as estimate)
Example:
(230) x (460) x (1.732) x (0.85)
x 4,160 x $0.05
1,000
= $ 32,398 per year
6. How to
Convert Acfm to Scfm
SCFM = ACFM x
(Actual Inlet Pressure/14.5) X (520/(Actual Inlet Temperature + 460) X RH%
correction (.995 to .97)
Example: 500
ACFM compressor at 14.3 psia and 95F and summer conditions 95F and 60% RH
SCFM = 500 x
(14.3/14.5) x (520/(95+460) x .97
= 448 scfm
Positive displacement compressor input power increases 1% for every 2 psi increase in discharge pressure
7. RECEIVER FORMULA
l Tank =Tank Height x (Tank Radius)² (Gallons)
73.53
l Tank =Tank Height X (Tank Radius)² (Cubic Ft)
l 550
l Tank =Pi(3.14) X (Tank Radius)²XHeight (Cubic Ft)
l Tank = 23.5 X (Tank Radius)² X Height (Gallons)
Gallons X 0.1337 = Cubic Feet
Cubic Feet X 7.48052= Gallons
8. Compressed Air Storage Primary Formula
Capacitance calculations:
The size of the event in CF (rate of flow X duration)
Divided by the allowable pressure drop in PSI = the required capacitance in CF/PSI, then convert to gallons (X 14.5 psi per atmosphere X 7.48 gal/cf)
Or, divided by the capacitance in CF/PSI = the pressure drop in PSI


9. HEADER STORAGE
Compressed air moves at a limited velocity inside the pipe;
approximately 250 linear feet per second at 1.0 psid and 100 psig
Header Storage Problem
How will the startup of a 600 scfm application located 1000 feet in header distance from the compressor room impact the header pressure? The piping consists of 600 ft of 4 and 1015 ft of 3. Also, assume that there is a flow controller in the system. What additional storage is required to control the pressure fluctuations to less than 2 psi?
Remember:
The size of the event in CF (rate of flow X duration)
Divided by the allowable pressure drop in PSI =
the required capacitance (convert to gallons)
Or, divided by the capacitance in CF/PSI = the pressure drop in PSI
Header Storage Solution
Size of the event
This application will remove air from the header for (1000 ft / 250 fps) = 4 seconds at a rate of 10 scf/sec (600 scfm / 60 sec) = 40 scf
Divided by the capacitance
with the piping capacitance at 7.25 scf/psi, the
pressure will drop
(40 scf / 7.25 scf/psi) = 5.5 psi.
Assuming we want to control the
pressure drop to less than 2 psi, the storage requirement would be:
(40 scf / 2 psid) X 14.5 psia = 290 scf X 7.48gal/cf = 2,169 gallons. You can subtract the existing volume contained in the header piping from this figure if it is significant (786 gallons in this example).

